electrician carpenters
We arrived in week 47th On Tuesday I had a constructive meeting with our construction manager. The result was a tight schedule is that we do provide einheizen in KW 51st
have been there this week and the electricians are already completely through. Colleagues from B & O come to the cleaners again by the implement 2nd phase of installation (use the wall outlets, cabinet install, etc. pp.). Furthermore, should come today or tomorrow, the carpenters at the sub-strokes to install.
As of today, then again to support our masons in use around the sills, at least the first floor, next Monday as the scaffolding comes off. The only drawback here ... because it is very cold at the moment, I can delete the remaining sub blows probably until spring, well, let's see. should
roadmap provides otherwise come before the week 48 II drywall and plastering, plumbing & heating week 49 and week 50 floor, dirt, water and electrical company with electricity and gas supply ...